Concrete Work Update Photos – 04 October 2017
Concrete work continues; you can see the update photos of concrete work
Stone Retaining Walls Completed – 18 September 2017
Stone wall work is completed by our team by 18 September 2017
Concrete Work Started – 11 September 2017
Concrete work team for villas arrived from Turkey. We expect to finish
Stone Retaining Walls Started – 22 June 2017
Stone wall team arrived to Bosnia from Turkey and started to work.
Excavation Started – 16 April 2017
Due to the slope on the land, there is great amount excavation